the process
1
Contact a friendly HomeZone sales executive
2
Choose a functional HomeZone design and or discuss your personal requirements
3
If changes are significant HomeZone will arange to have sketch plan drawn to make sure we are all on the same page.
4
HomeZone to visit site where available to identify any concerns.
5
HomeZone to price up your design and provide you a quotation.
6
Deal details agreed
7
Enter into a preliminary works agreement (pwa)
8
HomeZone to arrange for feature site survey subject to land title availabillty.
9
HomeZone to arrange for Structural engineers site report subject to land title being available.
10
HomeZone to provide building file with current docs and colour selection information.
11
HomeZone to prepare working drawings.
12
HomeZone to verify all site costs to the best of our abillity so they are no nasty surprises later on.
13
Contract documents completed and reviewed with client.
14
Contract signed / where applicable balance of deposit paid.
15
Plans, Specifications, Engineers details submitted to local council for their approval.
16
Plans submitted to water authority for their approval.
17
Client to finalise material selections (bricks, window, roof, ceramic tiles, laminates etc).
18
Pre-start meeting with HomeZone colour consultant.
19
Client to provide details of finance approval.
20
Client to provide proof of land ownership.
21
Shire and Water board approval received.
22
Final plans and documents signed and received by builder.
23
Ok to start. Proceed to construction.
24
Ok to start constuction phase
25
Quanties finalised and orders placed
26
Water meter and temporary power called
27
Site re pegged
28
Earth-works completed
29
Concrete footings and slab
30
Sewage Drains installed.
31
Brick load. Bricks frames lintels, cement.
32
Bricklayer commences.
33
Bricklaying completed (plate height).
34
Roof load delivered. Timber, Steel, Hardware.
35
Carpenter commences.
36
Plumbing and Electrical tube.
37
Gutters installed.
38
Roof cover proceeds
39
Site clean up.
40
Plaster float.
41
Ceilings and Cornice installed.
42
Glazing to windows.
43
Plaster set coat to walls.
44
Hang /Swing external doors. We are now at "Lock-Up".
45
House locked up.
46
Fixing carpentry installs doors, shelving.....
47
Plumber installs bath etc. ready for the cabinet maker to come in.
48
Cabinet worker commences installation.
49
Ceramic tiling and Waterproofing.
50
Garage hardstands, drives and paths.
51
Painting started.
52
Plumbing and Gas fit off
53
Electrical Installation
54
Shower screens and Mirrors.
55
Plaster Patch.
56
Painting completed.
57
House Clean.
58
Site Clean
59
Builder meets client and conducts Practical Completion inspection.
60
Inspection items completed.
61
Client to make final payments.
62
Hand over of keys to client.
63
Client moves into new home very happy.
64
During house warming party friends and family are impressed by the quality and ask for Builders details.
65
Clients receives spotters fee for recommendation of future clients.